We’ve been given the OK by JH admin to start working on this during the last week of school. Minimal instruction will be going on.
Things to do in Mid May:
- Identify long VGA cables (and others) we don’t use anymore in classrooms. Remove and /or coil up and tie off to building supports.
- Coil up old network cables in classrooms that aren’t in use, but one day we might
- Label camera cables and cameras with matching identifiers. – SHARPIE
- Verify audio works in room prior to tear down.
- Verify LRC at MIS is open for JH cleaning, etc.
Things to do:
- Figure out a process for labeling/removing/relocating technology equipment from rooms.
- 8th grade chromebooks need to be moved to another building.
- Pile on pallets at LRC – move MIS
- Melendez will need to be moved to another building.
- Tear down cameras in hallways, tie the cables up in the ceiling
- Identify long VGA cables (and others) we don’t use anymore in classrooms. Remove and /or coil up and tie off to building supports. Push copiers into LRC for imagetec pickup
Tearing down rooms:
- Phones need to be labeled and removed from rooms
- APs need to be labeled and removed from rooms
- Projectors/ w mounts need to be labeled and removed from rooms
- Speakers need to be disconnected Remove any cabling that teachers use (network, audio, VGA, etc)
- Extra devices (chromebooks, chargers, document cameras) need to be labeled and removed from rooms.
...