Task

Due

JES

WT

MES

MPC

MIS

JH

AUX

Rival 5 Phone Review

6/1

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Set up Summer IVR on main phone lines

6/5

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Room Teardown

  • Phones

  • Cables

  • Laptops

6/2

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Turn off AV amps / cabinets

6/2

  •  

  •  
  •  
  •  

Email Groups Updated

  • All transfers / job swaps

6/23

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Clean Projectors

8/1

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Inventory of Chromebooks, Ipads, etc

7/3

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Keystone jacks inspected & ordered

7/3

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Inspect all turned in ipads / kickstands

7/3

  •  
  •  
  •  
  •  

  •  

Inspect all turned in chromebooks

7/3

  •  
  •  
  •  

  •  
  •  

Resigned/Retired Teacher Laptops Imaged and Updated

7/3

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Teachers Laptops Distributed / Ready

July?

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Rooms Set Up and Tested

8/1

  •  
  •  
  •  
  •  
  •  
  •  
  •  

Mimios Distributed as appropriate

8/1

  •  
  •  
  •  

  •  

Plan on new student growth.

  • Have at least 5 devices per grade ready

8/16

  •  
  •  
  •  

  •  
  •  
  •  

K-2 Clever Badges

8/16

  •  
  •  
  •  

  •  

4th Grade CB Inspection /Collection

7/3

  •  
  •  
  •  

  •  

Major Summer Projects:

Title & Owner

Description / Sub Tasks

  •  2nd and 5th Grade CB Deploy

Checklist:

Unpack, inventory, enroll CB

Assign students to machine, label and case. QR Code print for 2nd grade.

  •  K and move in 1st grade Ipad Deployment

Checklist:

Clean existing ipads, wipe data from them, configure in new role. QR Code print

  •  MPC and WT Teacher laptops Deployed

...

Project Title

Due

Done?

Description

Why

Mist Install

  •  

Replacing Campus APs

Contract up with Ruckus, switching to Mist APs for a different experience.

MES Fortigate Router Config

  •  

Setting up MES fortigate as Router

Better visulaization and more robust security

JH ICN INternet

  •  

New internet for Campus

VLAN Reconfigure

  •  

Re configuring VLANs

Better future with radius for wifi and other uses IE tech vlan

MFA RDP/VPN/Backups

  •  

MFA

Security

Copier Install

  •  

New Copiers plus print servers and Papercut server

Virtual Server Rebuilds

  •  

Rebuilding remaining 2012 Servers

Server 2012 is coming end of life soon

D201masterdc Decomision

  •  

Decommisioning server AD/SMTP/DNS/printing/etc.

Hardware is aging

...

Project Title

Due

Done?

Lead?

Description

Why/Reason?

PS EOY Rollover

  •  

Pam

  •  Notify admins / secretaries about roll

New Student Delievery

  •  

Pam

Start working on delivery of new students for the 23-24 school year from registration

To get new students into PS.

Returning Student Delievery

  •  

Pam

Start working on delivery of returning students for the 23-24 school year from registration

Summer school implementation

6/2

Pam

  •  Create custom classes in Clever for summer school
  •  Ensure new staff / exisiting staff aren’t getting disabled who are working summer school
  •  Get in contact with IXL and Seesaw to process a manual sync after Clever classes have been created

Ensure a smooth summer school rollout.

/wiki/spaces/TK/pages/1340932101

ByteCurve/ Zonar GPS Rollover

8/1

Aaron

  •  Aaron Souza Figure out rollover process for students in Mycurve
  •  TBAssigned: Figure out new campus “name” scheme and update throughout system
  •  Update routes/keys/buses as appropriate.
  •  Announce new routes etc when transportation goes live in August.

...

Project Title

Due

Status / Owner

Description

Why/Reason?

Run cable for RLock pull station at JH

Run cable to admin hallway across form Jess Rios office for future install.

Run cable for RLock pull station, hallway camera, future gym camera at AUX

Run cables to AED station, corner hallway near gym and future job inside gym

Run cable for RLock pull station, hallway camera, future gym camera at AUX

Run cables to AED station, corner hallway near gym and future job inside gym

Run cable for Rlock pull station and MPC hallway camera

Cables should go past Terryi’s office with a loop for future placement. Plan on one camera shooting west (down hall) near vestibule.

Vertical Digital Signage TV @ MIS

Install/mount TV in old Trophy case by main entrance. Configure Raspberry Pi for Signage.

...