Summer 2023-2024

Summer 2023-2024

*JH Teardown (Needs to be done before 5/26)*

JH Teardown 23/24

Summer Building 2023 Check List

Task

Due

JES

WT

MES

MPC

MIS

JH

AUX

Task

Due

JES

WT

MES

MPC

MIS

JH

AUX

Rival 5 Phone Review

6/1

Set up Summer IVR on main phone lines

6/5

Room Teardown

  • Phones

  • Cables

  • Laptops

6/2

Turn off AV amps / cabinets

6/2

 

 

 

Email Groups Updated

  • All transfers / job swaps

6/23

Clean Projectors

8/1

Inventory of Chromebooks, Ipads, etc

7/3

Keystone jacks inspected & ordered

7/3

Inspect all turned in ipads / kickstands

7/3

 

 

Inspect all turned in chromebooks

7/3

 

 

Resigned/Retired Teacher Laptops Imaged and Updated

7/3

Teachers Laptops Distributed / Ready

July?

Rooms Set Up and Tested

8/1

Mimios Distributed as appropriate

8/1

 

 

 

Plan on new student growth.

  • Have at least 5 devices per grade ready

8/16

 

K-2 Clever Badges

8/16

 

 

 

4th Grade CB Inspection /Collection

7/3

 

 

 

 

 

Major Summer Projects:

Title & Owner

Description / Sub Tasks

Checklist:

Unpack, inventory, enroll CB

Assign students to machine, label and case. QR Code print for 2nd grade.

Checklist:

Clean existing ipads, wipe data from them, configure in new role. QR Code print

“Big Tech”Summer Projects

Project Title

Due

Done?

Leader

Description

Rival 5

 

 

Replacing our phone system with Rival 5.

Crisis Go Implementation

 

 

 

Implementing CrisisGo for teachers / staff /

MDF Environmental Monitoring

 

 

Joey / Andrew

Find a environmental monitoring system for our MDF’s.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Networking Summer Tasks

Project Title

Due

Done?

Description

Why

Mist Install

 

Replacing Campus APs

Contract up with Ruckus, switching to Mist APs for a different experience.

MES Fortigate Router Config

Jun 16, 2023

Setting up MES fortigate as Router

Better visulaization and more robust security

JH ICN INternet

Jun 30, 2023

New internet for Campus

 

VLAN Reconfigure

Jul 25, 2023

Re configuring VLANs

Better future with radius for wifi and other uses IE tech vlan

MFA RDP/VPN/Backups

Aug 11, 2023

MFA

Security

Copier Install

Aug 1, 2023

New Copiers plus print servers and Papercut server

 

Virtual Server Rebuilds

Aug 7, 2023

Rebuilding remaining 2012 Servers

Server 2012 is coming end of life soon

D201masterdc Decomision

Jun 30, 2023

Decommisioning server AD/SMTP/DNS/printing/etc.

Hardware is aging

 

Systems Summer Tasks

Project Title

Due

Done?

Lead?

Description

Why/Reason?

PS EOY Rollover

 

Pam

 

New Student Delievery

 

Pam

Start working on delivery of new students for the 23-24 school year from registration

To get new students into PS.

Returning Student Delievery

 

Pam

Start working on delivery of returning students for the 23-24 school year from registration

 

Summer school implementation

6/2

 

Pam

Ensure a smooth summer school rollout.

Confluence page

ByteCurve/ Zonar GPS Rollover

8/1

 

Aaron

 

 

 

 

 

 

 

 

 

 

 

 

 

Maintenance and Tech Projects:

Project

Lead

Date

Description

Project

Lead

Date

Description

JH HVAC

Maint

5/26/2023

Jr. High ceilings being completely removed. See JH Teardown 23/24 for more details.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Hired out Projects

Project

Vendor

Dates

Status

Description

Project

Vendor

Dates

Status

Description

Jones LRC Electrical

“Lipitor Electric” friend of Glenn W.

Mid July

Scheduled for mid-july (walked down 6/30, he will mount TV brackets for us and HDMI raceway)

Left VM to establish contact

Run 110v and racway to future TV installation

MES Intercom Paging

ITR

6-30

Installed. Going to return with a call button for room off LRC.

Install itercom speaker in the cafe “storage room” and the new office off library.

MIS Gym Screen

Likely Concert Sound

Early July

Installed & operational

New screen for projectors to display on-- due to new curtain at MIS gym

New Gym screen has a white area for projection. Its not perfect but it works for our purposes.

MES cafe/gym Projector

Velocita

 

Waiting on Quote

Hang projector and screen for Cafe to project on to. Gym projector replacement possible at MES.

Misc. Other Tasks

Project Title

Due

Status / Owner

Description

Why/Reason?

Run cable for RLock pull station at JH

Jun 30, 2023

Run cable to admin hallway across form Jess Rios office for future install.

 

Run cable for RLock pull station, hallway camera, future gym camera at AUX

Jun 30, 2023

Run cables to AED station, corner hallway near gym and future job inside gym

 

Run cable for RLock pull station, hallway camera, future gym camera at AUX

Jun 30, 2023

Run cables to AED station, corner hallway near gym and future job inside gym

 

Run cable for Rlock pull station and MPC hallway camera

Jul 7, 2023

Cables should go past Terryi’s office with a loop for future placement. Plan on one camera shooting west (down hall) near vestibule.

 

Vertical Digital Signage TV @ MIS

Aug 8, 2023

Install/mount TV in old Trophy case by main entrance. Configure Raspberry Pi for Signage.

 

 

 

 

 

Summer OverView

22-May202329-May05-Jun12-Jun19-Jun26-Jun03-Jul10-Jul17-Jul24-Jul31-Jul07-Aug14-Aug21-Aug28-Aug
IT Support
Ed Tech
Communications
Automation

Feature 1

Feature 2

Aux new Cabling

8th Grade CB

4th Grade CB

Collect K,1,4,8 Devices

Ipad Reconfiguration

5th Grade CBs

2nd Grade CBs

Install new Admin Phones

New Firewall Install

Organize / Evaluate CBs for New Sale

Identify Broken turned in Units

Ipad kickstands

Support Extended Summer School & Course Recovery

Support Camp Minooka

Support Camp Minooka

Enrichment Camp

Feature 3

SOPPA iPad Apps

SOPPA CB Sites

Identify all broken keystones

Replace broken Phones

New Teacher How To

Install Campus Projectors

Install new phones

New Staff Laptops

Update Parent How To

Tech Training by Aaron

All Techs PD Course

IDF / MDF Clean up

PS EOY Roll

UC EOL

 

 

Completed Tasks:

 

 

 

 

 

 

 

 

 

 