Summer 2024-2025

Summer 2024-2025

Summer Building 2024 Check List

Task

Due

JES

WT

MES

MPC

MIS

JH

AUX

Task

Due

JES

WT

MES

MPC

MIS

JH

AUX

Confirm Lockdown Buttons on Phones

7/26

Set up Summer IVR on main phone lines

 

Room Teardown

  • Phones

  • Cables

  • Laptops

5/31

Turn off AV amps / cabinets

5/31

 

 

Email Groups Updated

  • All transfers / job swaps

 

Clean Projectors

8/1

Keystone jacks inspected & ordered

5/31

Resigned/Retired Teacher Laptops Imaged and Updated

7/26

Rooms Set Up and Tested

7/26

Inventory of Spare Devices Done

7/26

Mimios Distributed as appropriate

7/26

 

 

 

Plan on new student growth.

  • Have at least 5 devices per grade ready

8/9

 

K-2 Clever Badges

8/13

 

 

 

Inspection of turned-in HP laptops

6/7

 

 

 

 

Counting / Organizing Old Windows laptops to upgrade to turned in HPs.

6/7

 

 

 

 

K4 Ipad Deployment

8/13

 

 

 

New Chromebook Deployment

8/13

 

 

Camera Installs

7/26

AP Deployment

6/14

 

 

Set IVR back to normal

 

Inspect all cameras for positioning and focus

7/26

Algo Light Install

7/26

Clean / Image Computer for Staff Sale

6/21

Building Technician Advanced / Progress Projects:

https://trello.com/b/ODrTEMGt/tech-summer-projects

 

Department Summer Projects

Project Owner and Title

Due

Description / Documentation:

Project Owner and Title

Due

Description / Documentation:

Jun 21, 2024

Clean / Image laptops for staff sale.

Aug 9, 2024

Board Room AV Upgrade Project.

Aug 9, 2024

Glen approved – hiring some electrician to install an outlet. He’s thinking about conduit. Project Summary:

May 24, 2024

  • Confirm with the security team the exact locations

Jul 12, 2024

Project:

Jul 22, 2024

Bus Camera Fleet install by Provision. Provision coming out July 22-August 1.

May 31, 2024

Install new copper cables at MIS, fiber at WT and fiber at JH by Eric from Total Solutions. Begins 5/28 estimated completion 5/31

Jun 4, 2024

ITR to install new audio equipment at wood gym at JH. Begins 6/3

 

 

 

Network Tasks

Project Owner and Title

Due

Description / Documentation:

Project Owner and Title

Due

Description / Documentation:

Jul 1, 2024

Upgrade both internet connections from 1gbps to 2gbps

Jun 14, 2024

All new Mist access points installed and tested

Jun 7, 2024

Upgrade switches from MES purchase to eliminate all EX 2200 models

Jun 14, 2024

All switches reconfigured to be managed by Mist interface

Jun 4, 2024

ATT managed AUX <> MES link installed and working

Jun 21, 2024

Radius configured, tested and implemented district wide

Jun 27, 2024

Full-blown Disaster Recovery Test / Simulation. @Aaron Souza @Matthew Shackley

Jul 1, 2024

All closets inspected, cleaned up and critical cables labeled.

  • MIS MDF/Cafe IDF

  • JH MDF/LRC IDF

  • AUX IDF

  • MPC MDF/ IDF Rm 113/ Upstairs IDF

Jun 21, 2024

Technology Staff Vlan configured and rolled out for enhanced security

Data Projects

Project Owner and Title

Due

Description / Documentation:

Project Owner and Title

Due

Description / Documentation:

Jul 5, 2024

https://trello.com/c/6KxJZWaf https://trello.com/c/veLOF5Xf

Aug 7, 2024

All new students are delivered to PS. https://trello.com/c/Bume97ro

Aug 7, 2024

All returning students delivered/updated in PS. https://trello.com/c/iljeIXAT

Jul 11, 2024

Ensure a smooth summer school rollout. Confluence page

Aug 9, 2024

Jul 12, 2024

Update data syncs to Versatrans including new fields. https://trello.com/c/lKwkRZMv

Jul 1, 2024

Promote all student accounts to 24-25 grade year https://trello.com/c/ZuPCbLt9

Jul 12, 2024

https://trello.com/c/RxuaRHw5

Jul 31, 2024

https://trello.com/c/LAbrrYUP

Aug 9, 2024

Bulk PDF yearly health form information for nurses for new and returning students.

Jun 28, 2024

@David Plaskett @Aaron Souza Review at high-level new data dashboard systems. eduClimber, Scholastycs (email from Aaron), DCR insights (PSUG)

Jul 1, 2024

Finalize the snap program roll over with Amy.

 

 

District Technician

Project Owner and Title

Due

Description / Documentation:

Project Owner and Title

Due

Description / Documentation:

Jun 28, 2024

Update images for all of our teacher laptop models

Jun 28, 2024

Update Servers to new Windows versions for security

Jun 14, 2024

Set up all A/V equipment for board room in MPC gym.

Jul 12, 2024

Work with Maintenance and @Joseph Prusinski to remove 1-2 shelves in MIS MDF .

 

 

 

 

 

 

 

 

 

 

 

 

 

 